Roads19HI0044

CONCRETING OF ROAD, BRGY. SAN ROQUE, LILOAN, CEBU

CONCRETING OF ROAD, BRGY. SAN ROQUE, LILOAN, CEBU is a DPWH-tracked public work in Cebu 5th DEO, Region VII. Reported contract value: ₱1,875,767.11. Status: Reported complete (DPWH). Contractor on record: JOHN ARNE CONST. Figures trace to dpwh.

Cebu 5th DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-19-0012920

₱136,500.00 · FY2019

Released to Allowan Ponso National High School “A”and Cash r (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

55 projects · ₱172.2M total · 0 flags

Other projects by this contractor

View all 55 projects →

4. Implementation

Contract Amount

₱1,875,767.11

Progress

Reported complete (DPWH)

Start Date

July 17, 2019

Target End

August 22, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.