Construction of Drainage Structure23MB0033

Construction of Drainage System (Box Culvert), Purok 6, Barangay Bunao, Tupi, South Cotabato

Construction of Drainage System (Box Culvert), Purok 6, Barangay Bunao, Tupi, South Cotabato is a DPWH-tracked public work in TUPI (SOUTH COTABATO), SOUTH COTABATO, Region XII. Reported contract value: ₱4,948,882.27. Status: Reported complete (DPWH). Contractor on record: ROCKSTONE CONST SERVICES & SUPPLY. Figures trace to sumbong.

TUPI (SOUTH COTABATO), SOUTH COTABATO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Road with Lined Canal/ Flood Control at Barangay Danlag, Tampakan, South Cotabato
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-23-0021169

₱646,190.00 · FY2023

Released to Bagamanoc Rural Development High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱4.9M total · 0 flags

4. Implementation

Contract Amount

₱4,948,882.27

Progress

Reported complete (DPWH)

Start Date

July 20, 2023

Target End

December 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.