Flood Control and Drainage15DP0120

FLOOD CONTROL PROJECTS BASED ON FLOOD MASTER PLAN FOR METRO MANILA AND SURROUNDING AREAS CONSTRUCTION OF FLOOD CONTROL STRUCTURE (UPSTREAM AND DOWNSTREAM) OF PATAY NA TUBIG BRIDGE, SAN PABLO CITY, LAGUNA 3RD LD

FLOOD CONTROL PROJECTS BASED ON FLOOD MASTER PLAN FOR METRO MANILA AND SURROUNDING AREAS CONSTRUCTION OF FLOOD CONTROL STRUCTURE (UPSTREAM AND DOWNSTREAM) OF PATAY NA TUBIG BRIDGE, SAN PABLO CITY, LAGUNA 3RD LD is a DPWH-tracked public work in Laguna 3rd DEO, Region IV-A. Reported contract value: ₱27,193,469.45. Status: Reported complete (DPWH). Contractor on record: NEWBIG FOUR J CONST INC FORMERLY: FOUR J CONST. Figures trace to dpwh.

Laguna 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control Projects based on Flood Master Plan for Metro Manila and Surrounding Areas - Construction of Flood Control Structure (Upstream and Downstream) of Patay na Tubig Bridge, San Pablo City, Laguna
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-16-0030618

₱655,280.00 · FY2016

Released to Zamboanga Sibugay National High School (Pangi Re (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱27,193,469.45

Progress

Reported complete (DPWH)

Start Date

February 23, 2016

Target End

August 20, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.