Roads22K00112

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, PANGUIL BAY ACCESS ROAD, TUBOD SIDE, LANAO DEL NORTE

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, PANGUIL BAY ACCESS ROAD, TUBOD SIDE, LANAO DEL NORTE is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱75,266,857.31. Status: Reported complete (DPWH). Contractor on record: LANAO BUILDER AND ENT. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱75,266,857.31

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

October 8, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.