GAA 2023 CSSP23FC0051

CONSTRUCTION OF CALERO - PARANG - POBLACION BYPASS ROAD (PHASE IV), JOSE PANGANIBAN, CAMARINES NORTE

CONSTRUCTION OF CALERO - PARANG - POBLACION BYPASS ROAD (PHASE IV), JOSE PANGANIBAN, CAMARINES NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱95,568,261.25. Status: Reported complete (DPWH). Contractor on record: C B GARAY PHILWIDE BUILDERS. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Phase 4), Barangay San Antonio, Labo, Camarines Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-23-001968

₱52,690,068.00 · FY2023

Released to Eastern Samar State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱95,568,261.25

Progress

Reported complete (DPWH)

Start Date

April 5, 2023

Target End

June 29, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.