Roads21KA0102

REHABILITATION /RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS,SLOPE COLLAPSE AND LANDSLIDE ALONG KAPALONG -TALAINGOD -VALENCIA (BUKIDNON)RD K1575 + 600 - K1575 + 800SAN FERNANDO, BUKIDNON

REHABILITATION /RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS,SLOPE COLLAPSE AND LANDSLIDE ALONG KAPALONG -TALAINGOD -VALENCIA (BUKIDNON)RD K1575 + 600 - K1575 + 800SAN FERNANDO, BUKIDNON is a DPWH-tracked public work in Bukidnon 1st DEO, Region X. Reported contract value: ₱17,640,000.00. Status: Reported complete (DPWH). Contractor on record: JT GAMOLO CONST INCORPORATION FORMERLY:J T GAMOLO CONST. Figures trace to dpwh.

Bukidnon 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures within Mindanao River Basin (along Pulangui River), Downstream of New Batangan Bridge, Barangay Poblacion Section, Valencia City, Bukidnon
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-D-21-0001553

₱34,847,000.00 · FY2021

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

175 projects · ₱6.3B total · 0 flags

4. Implementation

Contract Amount

₱17,640,000.00

Progress

Reported complete (DPWH)

Start Date

March 15, 2021

Target End

October 8, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.