Buildings and Facilities17DM0157

CONSTRUCTION OF THREE-STOREY NINE-CLASSROOM SCHOOL BUILDING AT CAMFLORA NHS, SAN ANDRES, QUEZON

CONSTRUCTION OF THREE-STOREY NINE-CLASSROOM SCHOOL BUILDING AT CAMFLORA NHS, SAN ANDRES, QUEZON is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱21,877,354.87. Status: Reported complete (DPWH). Contractor on record: RAPID FOREMOST CONST CO. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Hingoso River, San Isidro Ibaba-San Vicente Section, General Luna, Quezon
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0021010

₱300,000,000.00 · FY2017

Released to Regional Field Unit - V (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of Three-Storey Nine-Classroom School

₱21,877,354.87 · RAPID FOREMOST CONST. .

Contractor

A

314 projects · ₱9.5B total · 3 flags

Other projects by this contractor

View all 314 projects →

4. Implementation

Contract Amount

₱21,877,354.87

Progress

Reported complete (DPWH)

Start Date

December 28, 2017

Target End

October 23, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.