Rehabilitation / Major Repair of Flood Control Structure22FB0015

Rehabilitation of Quirangay River Wall, Camalig, Albay

Rehabilitation of Quirangay River Wall, Camalig, Albay is a DPWH-tracked public work in CAMALIG (ALBAY), ALBAY, Region V. Reported contract value: ₱24,498,153.50. Status: Reported complete (DPWH). Contractor on record: SISBRO CONST CORP FORMERLY: SISBRO CONST & SUPPLY. Figures trace to sumbong.

CAMALIG (ALBAY), ALBAY, Region V
Region: Region V

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2022 · ₱50,000

    Probable match · score 0.90

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROV-22-0007373 · ₱645,834 · release to the district office, not itemized per project

    Possible match · score 0.68

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱23,501,303 · SISBRO CONSTRUCTION & SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-02-14 → 2019-02-14

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Albay

Based on the coordinates published with the DPWH record and NOAH file Albay.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: Rehabilitation of Quirangay River Wall, Camalig, Albay

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Suha Flood Control Dike in Camalig, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-22-0007373

₱645,834.00 · FY2022

Released to Homapon High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001730

₱80,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001631

₱60,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003024

₱50,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002890

₱2,150,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001623

₱40,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001966

₱40,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001965

₱20,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002436

₱47,688,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001737

₱187,700,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002950

₱120,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Rehabilitation of Quirangay River Wall, Camalig, A

₱23,501,302.80 · SISBRO CONSTRUCTION & SUPPLY

Award / contract ref: 22FB0015

Contractor

B

33 projects · ₱1.6B total · 1 flags

4. Implementation

Contract Amount

₱24,498,153.50

Progress

Reported complete (DPWH)

Start Date

February 21, 2022

Target End

July 14, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.