Roads23PC0019

ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAMM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLPASE, AND LANDSLIDES-TERTIARY ROADS-CLAVERIA-CALANASAN-KABUGAO ROAD-K0666+264-K0666+349

ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAMM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLPASE, AND LANDSLIDES-TERTIARY ROADS-CLAVERIA-CALANASAN-KABUGAO ROAD-K0666+264-K0666+349 is a DPWH-tracked public work in Apayao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱47,034,248.68. Status: Reported complete (DPWH). Contractor on record: REBTRADE INTERNATIONAL CORP. Figures trace to dpwh.

Apayao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Calabigan Flood Control Structure, Barangay Calabigan, Luna, Apayao
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-23-0021169

₱646,190.00 · FY2023

Released to Bagamanoc Rural Development High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

61 projects · ₱4.4B total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SIBUYAN CIRCUMFERENTIAL ROAD, KO002+431-KO002+771, ROMBLON

Region IV-B, Region IV-B

2022₱259.0M
Reported complete (DPWH)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGT. PROGRAM, CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF FLOOD MITIGATION STRUCTURES ALONG DUMLOG RIVER (UPSTREAM) BARANGAY CARMEN,

Region VII, Region VII

2023₱193.0M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-NATIONAL ROADS AND BRIDGES-NATIONAL ROADS-PILI-TIGAON-ALBAY BDRY RD.-K0505+700.00-K0505+970.00, SAGNAY,CAMARINES SUR 4TH LEGISLATIVE DISTRICT

Region V, Region V

2021₱193.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AT BALILIHAN, BOHOL

Region VII, Region VII

2024₱192.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SEAWALL, PHASE 1, UBAY, BOHOL

Region VII, Region VII

2025₱188.5M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, MADELLA-DIANADIAWAN ROAD, PROVINCE OF AURORA

Region III, Region III

2022₱188.2M
Reported complete (DPWH)
View all 61 projects →

4. Implementation

Contract Amount

₱47,034,248.68

Progress

Reported complete (DPWH)

Start Date

April 5, 2023

Target End

January 16, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.