Flood Control and Drainage24H00028

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AT BALILIHAN, BOHOL

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AT BALILIHAN, BOHOL is a DPWH-tracked public work in Region VII, Region VII. Reported contract value: ₱192,899,999.99. Status: Past target date (DPWH On-Going). Contractor on record: REBTRADE INTERNATIONAL CORP. Figures trace to dpwh.

Region VII, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

61 projects · ₱4.4B total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SIBUYAN CIRCUMFERENTIAL ROAD, KO002+431-KO002+771, ROMBLON

Region IV-B, Region IV-B

2022₱259.0M
Reported complete (DPWH)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGT. PROGRAM, CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF FLOOD MITIGATION STRUCTURES ALONG DUMLOG RIVER (UPSTREAM) BARANGAY CARMEN,

Region VII, Region VII

2023₱193.0M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-NATIONAL ROADS AND BRIDGES-NATIONAL ROADS-PILI-TIGAON-ALBAY BDRY RD.-K0505+700.00-K0505+970.00, SAGNAY,CAMARINES SUR 4TH LEGISLATIVE DISTRICT

Region V, Region V

2021₱193.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SEAWALL, PHASE 1, UBAY, BOHOL

Region VII, Region VII

2025₱188.5M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, MADELLA-DIANADIAWAN ROAD, PROVINCE OF AURORA

Region III, Region III

2022₱188.2M
Reported complete (DPWH)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF DIKE AT SAN ANTONIO RIVER, BRGY. SAN ANTONIO, DUERO, BOHOL

Region VII, Region VII

2024₱173.6M
Past target date (DPWH On-Going)
View all 61 projects →

4. Implementation

Contract Amount

₱192,899,999.99

Progress

Past target date (DPWH On-Going)

Start Date

May 10, 2024

Target End

September 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.