Construction of Flood Mitigation Structure23BH0190

Construction of Flood Control Structure, Brgy. Cassap Fuera, Cauayan City, Isabela

Construction of Flood Control Structure, Brgy. Cassap Fuera, Cauayan City, Isabela is a DPWH-tracked public work in CITY OF CAUAYAN (ISABELA), ISABELA, Region II. Reported contract value: ₱74,228,662.29. Status: Reported complete (DPWH). Contractor on record: JWU CONST AND SUPPLY. Figures trace to sumbong.

CITY OF CAUAYAN (ISABELA), ISABELA, Region II
Region: Region II

Follow the peso

3 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2023 · ₱50,000

    Probable match · score 0.93

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-B-23-0022537 ·

    Possible match · score 0.63

    DBM release source ↗
  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2023-03-21 → 2025-06-02

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Site vs flood hazard · Project NOAH 100-year map

Medium flood hazard · Isabela

Based on the coordinates published with the DPWH record and NOAH file Isabela.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Santiago City, Isabela
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-23-0022537

₱0.00 · FY2023

Released to 0300008 Regional Office VIII - - (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

305 projects · ₱13.7B total · 52 flags

4. Implementation

Contract Amount

₱74,228,662.29

Progress

Reported complete (DPWH)

Start Date

May 30, 2023

Target End

April 2, 2024

5. Audit