Roads24IA0097

CONCRETING OF BRGY. MARVEL TO BRGY. LOOC FMR, PHASE II, BRGY. MARVEL AND BRGY. LOOC, CULABA, BILIRAN

CONCRETING OF BRGY. MARVEL TO BRGY. LOOC FMR, PHASE II, BRGY. MARVEL AND BRGY. LOOC, CULABA, BILIRAN is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱37,799,501.46. Status: Reported complete (DPWH). Contractor on record: LEDA CONST INC. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Sitio Lomboy Flood Control Structure, Phase 6, Brgy. Calumpang, Naval, Biliran
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-24-0016293

₱168,381.00 · FY2024

Released to Tarlac 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

181 projects · ₱9.4B total · 0 flags

4. Implementation

Contract Amount

₱37,799,501.46

Progress

Reported complete (DPWH)

Start Date

April 1, 2024

Target End

October 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.