Flood Control and Drainage23CL0069

CONSTRUCTION OF LAWS RIVER FLOOD CONTROL STRUCTURE INCLUDING RECHANNELING, UPSTREAM (NORTH APPROACH) PACKAGE 1, CANDELARIA, ZAMBALES

CONSTRUCTION OF LAWS RIVER FLOOD CONTROL STRUCTURE INCLUDING RECHANNELING, UPSTREAM (NORTH APPROACH) PACKAGE 1, CANDELARIA, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱95,438,599.14. Status: Reported complete (DPWH). Contractor on record: PASCAL CONST. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Marangla River Flood Control Structure, Package 1, Iba, Zambales
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-23-0024802

₱403,985.00 · FY2023

Released to Bukidnon State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

23CL0069 - LAWS RIVER FLOOD CONTROL PACKAGE 1

₱95,052,440.36 · PASCAL CONSTRUCTION

4. Implementation

Contract Amount

₱95,438,599.14

Progress

Reported complete (DPWH)

Start Date

April 12, 2023

Target End

March 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.