Flood Control and Drainage22IA0070

CONSTRUCTION OF SEAWALL, BARANGAY STO. ROSARIO, NAVAL, BILIRAN (11.556509, 124.396287 TO 11.557006, 124.395725)

CONSTRUCTION OF SEAWALL, BARANGAY STO. ROSARIO, NAVAL, BILIRAN (11.556509, 124.396287 TO 11.557006, 124.395725) is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱4,698,082.60. Status: Reported complete (DPWH). Contractor on record: K. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Sitio Lomboy, Phase 5, Barangay Calumpang, Naval, Biliran
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-22-0004425

₱2,090,000.00 · FY2022

Released to Home Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,698,082.60

Progress

Reported complete (DPWH)

Start Date

February 21, 2022

Target End

May 6, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.