Flood Control and Drainage22IA0046

REHABILITATION OF UNGALI FLOOD CONTROL ALONG BILIRAN CIRCUMFERENTIAL ROAD, PHASE 4, KAWAYAN, BILIRAN (124.459130°, 11.688844° - 124.459263°, 11.689301°)

REHABILITATION OF UNGALI FLOOD CONTROL ALONG BILIRAN CIRCUMFERENTIAL ROAD, PHASE 4, KAWAYAN, BILIRAN (124.459130°, 11.688844° - 124.459263°, 11.689301°) is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱14,172,245.95. Status: Reported complete (DPWH). Contractor on record: K. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2022 · ₱25,000

    Probable match · score 0.92

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-D-22-0004425 · ₱2,090,000 · release to the district office, not itemized per project

    Possible match · score 0.61

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱14,172,246

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-03-28 → 2016-03-28

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Biliran

Based on the coordinates published with the DPWH record and NOAH file Biliran.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHABILITATION OF UNGALI FLOOD CONTROL ALONG BILIRAN CIRCUMFERENTIAL ROAD, PHASE 4, KAWAYAN, BILIRAN (124.459130°, 11.688844° - 124.459263°, 11.689301°)

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Ungali Flood Control along Biliran Circumferential Road, Phase 3, Kawayan, Biliran
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-22-0004425

₱2,090,000.00 · FY2022

Released to Home Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

22IA0046

₱14,172,245.95 · Awardee from PhilGEPS

Award / contract ref: 22IA0046

4. Implementation

Contract Amount

₱14,172,245.95

Progress

Reported complete (DPWH)

Start Date

February 21, 2022

Target End

July 10, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VIII (Eastern Visayas)BiliranKawayanUngale
Storms whose wind field reached it
Nokaen 2026Koto 2025Fung-Wong 2025Kalmaegi 2025Fengshen 2025
Hazard exposure
Flood (100-yr rain)LandslideDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.