Flood Control and Drainage25PK0015

ORGANIZATIONAL OUTCOME 2: PROTECTS LIVES AND PROPERTIES AGAINST MAJOR FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, COMPOP SONG-AK, MABILENG, LUBUAGAN,

ORGANIZATIONAL OUTCOME 2: PROTECTS LIVES AND PROPERTIES AGAINST MAJOR FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, COMPOP SONG-AK, MABILENG, LUBUAGAN, is a DPWH-tracked public work in Upper Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱1,954,854.65. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: MPD3 CONST. Figures trace to dpwh.

Upper Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Compop Song-ak, Mabileng, Lubuagan, Kalinga
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-25-0010316

₱3,575,360.00 · FY2025

Released to Upper Kalinga DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

12 projects · ₱130.8M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - PAVING OF UNPAVED ROADS: TERTIARY ROADS - LUBUAGAN-BATONG BUHAY-ABRA BDRY RD - K0459+(-260)-K0459+000, K0459+(-320)-K0459+(-287), K0459+(-350)-K0459+(-3

Upper Kalinga DEO, Cordillera Administrative Region

2024₱29.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: PAVING OF UNPAVED ROADS - TERTIARY ROADS: LUBUAGAN-BATONG BUHAY-ABRA BDRY RD - K0471+400 - K0472+054, LUBUAGAN, KALINGA

Upper Kalinga DEO, Cordillera Administrative Region

2024₱26.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION AND IMPROVEMENT OF THE PRESIDENTIAL SECURITY COMMAND HEADQUARTERS MANSION HOUSE DETACHMENT, THE MANSION HOUSE, ROMULO DRIVE, BRGY. LUALHATI, BAGUIO CITY

Cordillera Administrative Region, Cordillera Administrative Region

2024₱19.9M
Ongoing (DPWH-reported)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG

Upper Kalinga DEO, Cordillera Administrative Region

2025₱14.7M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING (WEAVING CENTER), LUBUAGAN, KALINGA

Upper Kalinga DEO, Cordillera Administrative Region

2024₱9.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (OPEN GYM) AT BNHS/SNHS, BARANGAY BANTAY AND BARANGAY SANTOR, TABUK CITY AND RIZAL, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2024₱5.9M
Past target date (DPWH On-Going)
View all 12 projects →

4. Implementation

Contract Amount

₱1,954,854.65

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 20, 2025

Target End

May 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.