Roads16CA0003

ASSET PRESERVATION OF NATIONAL ROADS- REHABILITATION/RECONSTRUCTION UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGED BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT AND MANAGEMENT-4 (HDM-4), TERTIARY ROADS ALONG JUNCTION LAYAC-BALANGA

ASSET PRESERVATION OF NATIONAL ROADS- REHABILITATION/RECONSTRUCTION UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGED BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT AND MANAGEMENT-4 (HDM-4), TERTIARY ROADS ALONG JUNCTION LAYAC-BALANGA is a DPWH-tracked public work in Bataan 1st DEO, Region III. Reported contract value: ₱14,512,011.20. Status: Reported complete (DPWH). Contractor on record: HORAMABI BUILDERS. Figures trace to dpwh.

Bataan 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 78%

UACS
18001
Amount
₱15,835,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures/Slope Protection, Talisay River, Sta 0+000 - Sta 0+805, Maluya - Cupang, Balanga City, Bataan
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-16-0028191

₱2,341,985.00 · FY2016

Released to 0000 - Presidential Communications Operations Office (PTo co (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Possible match · 67%

P.C.C.P.

₱560,908.00 · HORAMABI BUILDERS

Contractor

27 projects · ₱1.5B total · 0 flags

Other projects by this contractor

View all 27 projects →

4. Implementation

Contract Amount

₱14,512,011.20

Progress

Reported complete (DPWH)

Start Date

March 23, 2016

Target End

July 20, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.