Buildings and Facilities18BD0155

CONSTRUCTION OF THREE (3) STOREY TWELVE (12) CLASSROOM (TWO (2) CLASSROOM SCIENCE LABORATORY/TWO (2) CLASSROOM ICT & TWO (2) CLASSROOM REGULAR WORKSHOP BUILDING, TUAO VOCATIONAL AND TECHNICAL SCHOOL-PATA ANNEX, TUAO, CAG.

CONSTRUCTION OF THREE (3) STOREY TWELVE (12) CLASSROOM (TWO (2) CLASSROOM SCIENCE LABORATORY/TWO (2) CLASSROOM ICT & TWO (2) CLASSROOM REGULAR WORKSHOP BUILDING, TUAO VOCATIONAL AND TECHNICAL SCHOOL-PATA ANNEX, TUAO, CAG. is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱27,122,307.52. Status: Reported complete (DPWH). Contractor on record: E GUADIZ CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱30,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROII-18-0002813 · ₱6,117,152 · release to the district office, not itemized per project

    Possible match · score 0.80

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱27,122,308 · E. GUADIZ CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-08-02 → 2025-06-11

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF THREE (3) STOREY TWELVE (12) CLASSROOM (TWO (2) CLASSROOM SCIENCE LABORATORY/TWO (2) CLASSROOM ICT & TWO (2) CLASSROOM REGULAR WORKSHOP BUILDING, TUAO VOCATIONAL AND TECHNICAL SCHOOL-PATA  ANNEX, TUAO, CAG.

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System (Downstream), Natappian, Solana, Cagayan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROII-18-0002813

₱6,117,152.00 · FY2018

Released to Regional Office - II (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of Three (3) Storey Twelve (12) Class

₱27,122,307.52 · E. GUADIZ CONSTRUCTION

Award / contract ref: 18BD0155-re-ad

Contractor

C

106 projects · ₱1.1B total · 0 flags

4. Implementation

Contract Amount

₱27,122,307.52

Progress

Reported complete (DPWH)

Start Date

August 30, 2018

Target End

March 7, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.