Buildings and Facilities23GP0054

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY OYONG, SIGMA, CAPIZ

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY OYONG, SIGMA, CAPIZ is a DPWH-tracked public work in Capiz 2nd DEO, Region VI. Reported contract value: ₱4,939,998.88. Status: Reported complete (DPWH). Contractor on record: 3 A'S. Figures trace to dpwh.

Capiz 2nd DEO, Region VI
Region: Region VI

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2023 · ₱5,000 (shared by many projects, not this project's own line)

    Possible match · score 0.74

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROVIII-23-001968 · ₱52,690,068 · release to the district office, not itemized per project

    Possible match · score 0.58

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23GP0054 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2010-05-22 → 2025-07-28

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY OYONG, SIGMA, CAPIZ

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 74%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System in Barangay Binakayan (Covelandia Road and Tirona Highway), Kawit, Cavite
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-23-001968

₱52,690,068.00 · FY2023

Released to Eastern Samar State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,939,998.88

Progress

Reported complete (DPWH)

Start Date

April 17, 2023

Target End

October 13, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.