Construction of Flood Mitigation Structure22EF0069

Construction of Culasian River Flood Control Structure, Sta. 0+000 - Sta. 0+082, Rizal, Palawan

Construction of Culasian River Flood Control Structure, Sta. 0+000 - Sta. 0+082, Rizal, Palawan is a DPWH-tracked public work in RIZAL (MARCOS) (PALAWAN), PALAWAN, Region IV-B. Reported contract value: ₱9,653,000.00. Status: Reported complete (DPWH). Contractor on record: AFG CONST CORP. Figures trace to sumbong.

RIZAL (MARCOS) (PALAWAN), PALAWAN, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Culasian River Flood Control Structure, Sta. 0+000 - Sta. 0+150, Rizal, Palawan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-22-0011750

₱5,021,000.00 · FY2022

Released to Division of Davao Oriental (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002729

₱187,333,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002998

₱73,920,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002912

₱32,910,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0006799

₱2,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,653,000.00

Progress

Reported complete (DPWH)

Start Date

May 25, 2022

Target End

February 8, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.