Buildings and Facilities23HA0085

REHABILITATION OF PNP HEADQUARTERS, CAMP DAGOHOY, TAGBILARAN CITY, BOHOL

REHABILITATION OF PNP HEADQUARTERS, CAMP DAGOHOY, TAGBILARAN CITY, BOHOL is a DPWH-tracked public work in Bohol 1st DEO, Region VII. Reported contract value: ₱48,920,041.71. Status: Reported complete (DPWH). Contractor on record: VICTORIA DEVELOPMENT AND VENTURES CORP FOR: VICTORIA DEV'T AND CONST CORP. Figures trace to dpwh.

Bohol 1st DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Upstream and Downstream of Box Culvert at Tagbilaran North Rd (Tagbilaran-Jetafe Section) K0051+312, Tubigon, Bohol
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-23-0027493

₱6,643,934.00 · FY2023

Released to Eastern Samar State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

275 projects · ₱10.2B total · 0 flags

Other projects by this contractor

View all 275 projects →

4. Implementation

Contract Amount

₱48,920,041.71

Progress

Reported complete (DPWH)

Start Date

June 13, 2023

Target End

May 7, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.