Buildings and Facilities25PD0072

BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY QUEZON HILL PROPER, PHASE 2, BAGUIO CITY

BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY QUEZON HILL PROPER, PHASE 2, BAGUIO CITY is a DPWH-tracked public work in Baguio City DEO, Cordillera Administrative Region. Reported contract value: ₱4,702,500.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: HAIGHT'S CONST. Figures trace to dpwh.

Baguio City DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Phase 3, Barangay San Antonio Village, Baguio City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-25-0018627

₱55,000,000.00 · FY2025

Released to Bureau of Plant Industry (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

21 projects · ₱64.0M total · 0 flags

4. Implementation

Contract Amount

₱4,702,500.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 21, 2025

Target End

September 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.