Flood Control and Drainage20IH0023

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BRGY. ZONE 2 AND BRGY. LOOC, ALLEN, N. SAMAR

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BRGY. ZONE 2 AND BRGY. LOOC, ALLEN, N. SAMAR is a DPWH-tracked public work in Northern Samar 1st DEO, Region VIII. Reported contract value: ₱32,761,831.32. Status: Past target date (DPWH On-Going). Contractor on record: C A CONST AND SUPPLY. Figures trace to dpwh.

Northern Samar 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱33,454,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Brgy. Sabang Zone 2 and Brgy. Looc, Northern Samar
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Northern Samar 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱32,761,831.32

Progress

Past target date (DPWH On-Going)

Start Date

December 7, 2020

Target End

July 3, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.