Roads20GJ0033

CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD AT ZONE 1 (GONZALES AVENUE), BRGY. QUINTUIN SALAS, JARO, ILOILO CITY

CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD AT ZONE 1 (GONZALES AVENUE), BRGY. QUINTUIN SALAS, JARO, ILOILO CITY is a DPWH-tracked public work in Iloilo City DEO, Region VI. Reported contract value: ₱1,722,364.33. Status: Reported complete (DPWH). Contractor on record: BOAZ AND JACHIN CONST SUPPLY. Figures trace to dpwh.

Iloilo City DEO, Region VI
Region: Region VI

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2020 · ₱2,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱1,722,364

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-02-09 → 2025-11-28

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD AT ZONE 1 (GONZALES AVENUE), BRGY. QUINTUIN SALAS, JARO, ILOILO CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Zone 6, Barangay Bitoon, Jaro, Iloilo City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Iloilo City DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,722,364.33

Progress

Reported complete (DPWH)

Start Date

March 26, 2020

Target End

May 24, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.