Rehabilitation / Major Repair of Flood Control Structure24CG0026

Rehabilitation of Eroded Pampanga River Bank at Candating (Phase II), Arayat, Pampanga

Rehabilitation of Eroded Pampanga River Bank at Candating (Phase II), Arayat, Pampanga is a DPWH-tracked public work in ARAYAT (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱91,485,522.95. Status: Reported complete (DPWH). Contractor on record: EDDMARI CONST & TRADING. Figures trace to sumbong.

ARAYAT (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure with Road Dike along Sabangbalen River Phase 1, Mabalacat City, Pampanga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0018103

₱25,000,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008249

₱1,906,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005754

₱994,559.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0002412

₱426,959.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008250

₱176,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱91,485,522.95

Progress

Reported complete (DPWH)

Start Date

March 4, 2024

Target End

November 4, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.