Rehabilitation / Major Repair of Flood Control Structure23CG0041

Rehabilitation of Eroded Bank of Pampanga River at Candating, Arayat, Pampanga

Rehabilitation of Eroded Bank of Pampanga River at Candating, Arayat, Pampanga is a DPWH-tracked public work in ARAYAT (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱91,626,654.28. Status: Reported complete (DPWH). Contractor on record: EDDMARI CONST & TRADING. Figures trace to sumbong.

ARAYAT (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱47,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Maintenance of Flood Mitigation Structures along Quitangil River, Magalang, Pampanga - Phase 1
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Pampanga 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱91,626,654.28

Progress

Reported complete (DPWH)

Start Date

February 20, 2023

Target End

October 17, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.