Roads22AB0116

CONSTRUCTION OF ROAD, BARANGAY PASIL, PAOAY, ILOCOS NORTE

CONSTRUCTION OF ROAD, BARANGAY PASIL, PAOAY, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱19,010,720.62. Status: Reported complete (DPWH). Contractor on record: A B TAYLAN CONST. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2022 · ₱5,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 22AB0116 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2021-01-09 → 2025-04-24

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF ROAD, BARANGAY PASIL, PAOAY, ILOCOS NORTE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Slope Protection Wall), Barangay Daquioag, Marcos, Ilocos Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Ilocos Norte 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

98 projects · ₱4.4B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LAOAG-SAN NICOLAS BYPASS ROAD (LAOAG CITY-BACARRA SECTION), ILOCOS NORTE

Region I, Region I

2024₱238.8M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING - PRIMARY ROADS - MANILA NORTH ROAD - K0490+504-K0491+278; K0492+800-K0493+019; K0493+050-K0493+216; K0505+656-K0507+368; K0521+000-K0522+400; K0527+459-K0529+407; K0531+363-K0531+921; K0532+981-K0534+359

Region I, Region I

2018₱187.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, IMPROVEMENT/CONCRETING OF PAOAY LAKE CIRCUMFERENTIAL ROAD AND MALACANANG TI AMIANAN, PAOAY, ILOCOS NORTE

Region I, Region I

2017₱178.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - PAOAY-LAOAG INTERNATIONAL AIRPORT ACCESS ROAD, PAOAY, ILOCOS NORTE

Region I, Region I

2025₱156.0M
Past target date (DPWH On-Going)
No sat.

IMPROVEMENT/WIDENING OF NATIONAL ROADS ALONG N1 (S00034LZ), MANILA NORTH ROAD, K0494 + 396 - K0495 + 024; K0496 + 164 - K0496 + 423; K0496 + 775 - K0497 + 444; K0497 + 834 - K0498 + 000; K0499 + 200 - K0500 + 676; K0500+676 - K0500 +698(L/S); K0500 +676 -

Region I, Region I

2016₱146.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN), PAOAY-LAOAG INTERNATIONAL AIRPORT ACCESS ROAD, PAOAY, ILOCOS NORTE

Region I, Region I

2024₱145.1M
Past target date (DPWH On-Going)
View all 98 projects →

4. Implementation

Contract Amount

₱19,010,720.62

Progress

Reported complete (DPWH)

Start Date

March 25, 2022

Target End

July 13, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.