Flood Control and Drainage22OG0043

REHABILITATION OF DRAINAGE SYSTEM, BARANGAY PINYAHAN, QUEZON CITY

REHABILITATION OF DRAINAGE SYSTEM, BARANGAY PINYAHAN, QUEZON CITY is a DPWH-tracked public work in Quezon City 2nd DEO, National Capital Region. Reported contract value: ₱4,896,360.94. Status: Reported complete (DPWH). Contractor on record: E L ANOLIN CONST. Figures trace to dpwh.

Quezon City 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure, Laguna Creek, Barangay Kristong Hari, Quezon City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Quezon City 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,896,360.94

Progress

Reported complete (DPWH)

Start Date

February 18, 2022

Target End

May 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.