CONSTRUCTION OF THREE (3) STORY NINE (9) CLASSROOM SCHOOL BUILDING AT MAMPANG NATIONAL HIGH SCHOOL, BARANGAY MAMPANG, ZAMBOANGA CITY, ZAMBOANGA DEL SUR is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱27,512,446.46. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: SK PATH CONST AND SUPPLY. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2023 · ₱10,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23JA0101 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2023-01-01 → 2025-03-01

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF THREE (3) STORY NINE (9) CLASSROOM SCHOOL BUILDING AT MAMPANG NATIONAL HIGH SCHOOL, BARANGAY MAMPANG, ZAMBOANGA CITY, ZAMBOANGA DEL SUR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Ayala, Zamboanga City, Zamboanga del Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Zamboanga City 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱27,512,446.46

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

August 30, 2023

Target End

February 25, 2024