Roads22L00144

CONSTRUCTION OF GRAVEL ROAD - BUKIDNON - COMPOSTELA VALLEY ROAD (BRGY. NAMNAM, SAN FERNANDO, BUKIDNON - LAAK COMPOSTELA VALLEY) (PACKAGE 8), DAVAO DE ORO

CONSTRUCTION OF GRAVEL ROAD - BUKIDNON - COMPOSTELA VALLEY ROAD (BRGY. NAMNAM, SAN FERNANDO, BUKIDNON - LAAK COMPOSTELA VALLEY) (PACKAGE 8), DAVAO DE ORO is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱211,826,349.86. Status: Reported complete (DPWH). Contractor on record: ULTICON BUILDERS INC. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

546 projects · ₱133.2B total · 0 flags

4. Implementation

Contract Amount

₱211,826,349.86

Progress

Reported complete (DPWH)

Start Date

April 7, 2022

Target End

March 16, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.