Roads25CD0139

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS STA MARIA - NORZAGARAY RD K0033+900 - K0033+1010, K0034+000 - K0034+350, K0040+642 - K0040+1003

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS STA MARIA - NORZAGARAY RD K0033+900 - K0033+1010, K0034+000 - K0034+350, K0040+642 - K0040+1003 is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱39,703,853.72. Status: Past target date (DPWH On-Going). Contractor on record: 729 CONST INC FORMERLY 722 CONST INC. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bocaue-Santa Maria River and its tributaries (Tabon Creek), Sta. 04 + 830 - Sta. 04 + 900, Abangan Norte, Marilao, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

231 projects · ₱7.1B total · 9 flags

4. Implementation

Contract Amount

₱39,703,853.72

Progress

Past target date (DPWH On-Going)

Start Date

March 18, 2025

Target End

October 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.