DPWH transparency mirror

DPWH reports: Completed · 100%

Open DPWH portal record ↗

Publicly reported (according to cited sources)

  • Commission on Audit (fraud audit report) · 2025-09-25

    “the approved site already had an earlier existing flood control structure which could not have been built prior to the Joint Venture's receipt of the Notice to Proceed”
    Source link (external) ↗

Publicly reported by the cited sources; not a finding by this site. Criminal or administrative charges, where cited, are described as pending unless the source states a final judgment. Right of reply / submit evidence

Construction of Slope Protection Structure24CC0401

Construction/Improvement of Slope Protection Structure and Waterways along Bocaue River, Brgy. Turo (Sitio Hangga), Bocaue, Bulacan

Construction/Improvement of Slope Protection Structure and Waterways along Bocaue River, Brgy. Turo (Sitio Hangga), Bocaue, Bulacan is a DPWH-tracked public work in BOCAUE (BULACAN), BULACAN, Region III. Reported contract value: ₱98,994,958.26. Status: Reported complete (DPWH). Contractor on record: TOPNOTCH CATALYST BUILDERS INC / ONE FRAME CONST INC. Figures trace to sumbong.

BOCAUE (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Waterways and Flood Control Structure along Guiguinto River, Brgy. Malis, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007285

₱1,480,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005755

₱1,178,933.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0017916

₱440,428.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007286

₱137,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005756

₱95,671.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱98,994,958.26

Progress

Reported complete (DPWH)

Start Date

April 23, 2024

Target End

January 17, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.