Construction of Flood Mitigation Structure24EE0074

Construction of Slope Protection Structure along Lamoro Bridge 1, El Nido, Palawan

Construction of Slope Protection Structure along Lamoro Bridge 1, El Nido, Palawan is a DPWH-tracked public work in EL NIDO (BACUIT) (PALAWAN), PALAWAN, Region IV-B. Reported contract value: ₱44,097,774.54. Status: Reported complete (DPWH). Contractor on record: AR LUSTRE CONST CORP FORMERLY:A R LUSTRE JR CONST / A R L CONST. Figures trace to sumbong.

EL NIDO (BACUIT) (PALAWAN), PALAWAN, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱18,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Apurawan River Upstream ( L / S ) , Aborlan, Palawan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008379

₱1,809,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0018706

₱215,854.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008392

₱167,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱44.1M total · 0 flags

4. Implementation

Contract Amount

₱44,097,774.54

Progress

Reported complete (DPWH)

Start Date

February 14, 2024

Target End

November 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.