Flood Control and Drainage16AA0137

DAMAGED FC FACILITIES/STRUCTURES UNDER THE LRBFC & SABO PROJS-BANGUI FC, BANBAN RIVER D/S,LB ERODED

DAMAGED FC FACILITIES/STRUCTURES UNDER THE LRBFC & SABO PROJS-BANGUI FC, BANBAN RIVER D/S,LB ERODED is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱14,331,220.06. Status: Reported complete (DPWH). Contractor on record: FR ESPIRITU BUILDERS AND DEVELOPMENT CORP FORMERLY: FR ESPIRITU JR BUILDERS. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Damaged Flood Control Facilities/Structures under the Laoag River Basin Flood Control and Sabo Project (LRBDCSP) - Bangui Flood Control, Banban River U/S LB, Eroded Bank Revetment (Taguipuro Section)
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0024543

₱2,526,390.00 · FY2016

Released to Division of Northern Samar (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

76 projects · ₱2.1B total · 0 flags

4. Implementation

Contract Amount

₱14,331,220.06

Progress

Reported complete (DPWH)

Start Date

June 7, 2016

Target End

September 23, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.