Construction of Flood Mitigation Structure22AA0042

Construction/Rehabilitation of Flood Control Structure along Quibel River, Brgy. Kalaw, Dumalneg, Ilocos Norte

Construction/Rehabilitation of Flood Control Structure along Quibel River, Brgy. Kalaw, Dumalneg, Ilocos Norte is a DPWH-tracked public work in DUMALNEG (ILOCOS NORTE), ILOCOS NORTE, Region I. Reported contract value: ₱85,884,916.66. Status: Reported complete (DPWH). Contractor on record: FR ESPIRITU BUILDERS AND DEVELOPMENT CORP FORMERLY: FR ESPIRITU JR BUILDERS. Figures trace to sumbong.

DUMALNEG (ILOCOS NORTE), ILOCOS NORTE, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bislak River, Brgy. 8 to Brgy. Cabaroan, Bacarra, Ilocos Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002978

₱1,132,084,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003109

₱100,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0011001

₱100,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002617

₱25,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱85,884,916.66

Progress

Reported complete (DPWH)

Start Date

March 3, 2022

Target End

May 2, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.