Roads24PD0017

ROAD WIDENING-SECONDARY ROADS: MARCOS HI-WAY - (S00423LZ) CHAINAGE 000- CHAINAGE 140

ROAD WIDENING-SECONDARY ROADS: MARCOS HI-WAY - (S00423LZ) CHAINAGE 000- CHAINAGE 140 is a DPWH-tracked public work in Baguio City DEO, Cordillera Administrative Region. Reported contract value: ₱6,370,000.00. Status: Reported complete (DPWH). Contractor on record: W S FAGCANGAN CONST MANAGEMENT SERVICES. Figures trace to dpwh.

Baguio City DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Balili River ( Tributaries ) ( Sta 0 + 620 - Sta 0 + 793 ) , Baguio City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Baguio City DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

8 projects · ₱59.4M total · 0 flags

4. Implementation

Contract Amount

₱6,370,000.00

Progress

Reported complete (DPWH)

Start Date

March 27, 2024

Target End

July 17, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.