Construction of Flood Mitigation Structure24BC0097

Construction of Flood Control Structure along Chico River, Aquib, Piat, Cagayan (Package 1)

Construction of Flood Control Structure along Chico River, Aquib, Piat, Cagayan (Package 1) is a DPWH-tracked public work in PIAT (CAGAYAN), CAGAYAN, Region II. Reported contract value: ₱9,701,811.56. Status: Reported complete (DPWH). Contractor on record: DEKM CONST. Figures trace to sumbong.

PIAT (CAGAYAN), CAGAYAN, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Chico River, Aquib, Piat, Cagayan ( Package 1 )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010607

₱1,860,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0000878

₱1,207,156.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0005893

₱783,512.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0006344

₱15,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010618

₱172,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0000883

₱149,442.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0000879

₱102,960.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0001122

₱227,030.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

114 projects · ₱978.3M total · 0 flags

4. Implementation

Contract Amount

₱9,701,811.56

Progress

Reported complete (DPWH)

Start Date

April 4, 2024

Target End

July 20, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.