Construction of Flood Mitigation Structure22EF0035

Construction of Barong-barong Flood Control Structure, Sta. 0+500 - Sta. 0+745, Brooke's Point, Palawan

Construction of Barong-barong Flood Control Structure, Sta. 0+500 - Sta. 0+745, Brooke's Point, Palawan is a DPWH-tracked public work in BROOKE'S POINT (PALAWAN), PALAWAN, Region IV-B. Reported contract value: ₱11,674,127.13. Status: Reported complete (DPWH). Contractor on record: M C ESCALA CONST AND SUPPLY. Figures trace to sumbong.

BROOKE'S POINT (PALAWAN), PALAWAN, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Barong-barong Flood Control Structure, Sta. 0+500 - Sta. 0+700, Brooke's Point, Palawan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002729

₱187,333,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002998

₱73,920,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002912

₱32,910,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0006799

₱2,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱11,674,127.13

Progress

Reported complete (DPWH)

Start Date

May 25, 2022

Target End

December 16, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.