Buildings and Facilities23KK0122

CONSTRUCTION (COMPLETION) OF MUNICIPALITY COVERED COURT, BINUANGAN, MISAMIS ORIENTAL

CONSTRUCTION (COMPLETION) OF MUNICIPALITY COVERED COURT, BINUANGAN, MISAMIS ORIENTAL is a DPWH-tracked public work in Misamis Oriental 1st DEO, Region X. Reported contract value: ₱9,900,000.00. Status: Reported complete (DPWH). Contractor on record: L. Figures trace to dpwh.

Misamis Oriental 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project, Upstream of Dangoan Bridge 1, Medina, Misamis Oriental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Misamis Oriental 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,900,000.00

Progress

Reported complete (DPWH)

Start Date

June 8, 2023

Target End

November 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.