Buildings and Facilities24CL0011

CONSTRUCTION OF MULTI-PURPOSE BUILDING, SANTIAGO INTEGRATED SCHOOL, BARANGAY SANTIAGO, BOTOLAN, ZAMBALES

CONSTRUCTION OF MULTI-PURPOSE BUILDING, SANTIAGO INTEGRATED SCHOOL, BARANGAY SANTIAGO, BOTOLAN, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱16,822,025.29. Status: Past target date (DPWH On-Going). Contractor on record: THREE CM BUILDERS. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control / Slope Protection Works along Sto. Niño Creek, Capayawan, Botolan, Zambales
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Zambales 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Possible match · 70%

Improvement of Covered Court Brgy. Paco, Botolan,

₱396,842.15 · THREE CM BUILDERS

Possible match · 70%

LOT 1 PACKAGE CONCRETING OF CAPAYAWAN ALLEY ROAD

₱435,380.17 · THREE CM BUILDERS

4. Implementation

Contract Amount

₱16,822,025.29

Progress

Past target date (DPWH On-Going)

Start Date

March 25, 2024

Target End

November 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.