Construction of Flood Mitigation Structure25CF0012

Construction of Flood Mitigation Structure along Pampanga River, Barangay Pagas, Cabanatuan City, Nueva Ecija

Construction of Flood Mitigation Structure along Pampanga River, Barangay Pagas, Cabanatuan City, Nueva Ecija is a DPWH-tracked public work in CABANATUAN CITY (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱95,052,371.10. Status: Reported complete (DPWH). Contractor on record: CELSO C FERRER CONST CORP. Figures trace to sumbong.

CABANATUAN CITY (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Pampanga River, Barangay Calaba, San Isidro, Nueva Ecija
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-25-0007585

₱55,413,000.00 · FY2025

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-25-0000672

₱3,502,000.00 · FY2025

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-25-0012285

₱1,196,742.00 · FY2025

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-25-0008102

₱302,709,000.00 · FY2025

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-25-0000673

₱352,000.00 · FY2025

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-25-0019357

₱241,000.00 · FY2025

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-25-0015118

₱506,211.00 · FY2025

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

205 projects · ₱5.4B total · 3 flags

4. Implementation

Contract Amount

₱95,052,371.10

Progress

Reported complete (DPWH)

Start Date

February 20, 2025

Target End

February 5, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.