Roads23C00037

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, NEUVA ECIJA-AURORA ROAD, PROVINCE OF NUEVA ECIJA

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, NEUVA ECIJA-AURORA ROAD, PROVINCE OF NUEVA ECIJA is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱144,749,112.44. Status: Reported complete (DPWH). Contractor on record: CELSO C FERRER CONST CORP. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

205 projects · ₱5.4B total · 3 flags

4. Implementation

Contract Amount

₱144,749,112.44

Progress

Reported complete (DPWH)

Start Date

April 10, 2023

Target End

November 22, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.