Flood Control and Drainage25CD0039

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, STA. 01+990 - STA. 02+085 (UBIHAN - LIPUTAN - NAGBALON ROAD DIKE), MEYCAUAYAN CITY, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, STA. 01+990 - STA. 02+085 (UBIHAN - LIPUTAN - NAGBALON ROAD DIKE), MEYCAUAYAN CITY, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱93,604,419.93. Status: Past target date (DPWH On-Going). Contractor on record: 729 CONST INC FORMERLY 722 CONST INC. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Meycauayan River, Sta. 04+575-Sta. 04+675 (Liputan – Nagbalon Section), Meycauayan, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

25CD0039 - Construction of Flood Control Structure

₱93,604,419.93 · 729 CONSTRUCTION, . (FORMERLY: 722 CONSTRUCTION, .)

Contractor

B

231 projects · ₱7.1B total · 9 flags

4. Implementation

Contract Amount

₱93,604,419.93

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2025

Target End

October 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.