Water Provision and Storage24HA0146

IMPROVEMENT OF CALAPE WATERWORKS SYSTEM WITH SOLAR POWER SUPPLY FOR PUMPS, CALAPE, BOHOL

IMPROVEMENT OF CALAPE WATERWORKS SYSTEM WITH SOLAR POWER SUPPLY FOR PUMPS, CALAPE, BOHOL is a DPWH-tracked public work in Bohol 1st DEO, Region VII. Reported contract value: ₱2,963,000.00. Status: Reported complete (DPWH). Contractor on record: NENIAL CONST. Figures trace to dpwh.

Bohol 1st DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Abucayan Norte Flood Control, Abucayan Norte, Calape, Bohol
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bohol 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱2,963,000.00

Progress

Reported complete (DPWH)

Start Date

September 13, 2024

Target End

November 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.