Construction of Flood Mitigation Structure23HK0104

Construction of Banica River Control, Dumaguete City, Negros Oriental (Phase 1)

Construction of Banica River Control, Dumaguete City, Negros Oriental (Phase 1) is a DPWH-tracked public work in DUMAGUETE CITY (CAPITAL) (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII. Reported contract value: ₱29,700,000.00. Status: Reported complete (DPWH). Contractor on record: UY CONDEV CORP FORMERLY:UY CONST &. Figures trace to sumbong.

DUMAGUETE CITY (CAPITAL) (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bateria River (Upstream), Guihulngan City, Negros Oriental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Negros Oriental 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱29,700,000.00

Progress

Reported complete (DPWH)

Start Date

May 5, 2023

Target End

November 24, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.