Rehabilitation / Major Repair of Flood Control Structure22CK0085

Rehabilitation of existing Dike along Lucung River, (Culatingan Section, Left Bank), Concepcion, Tarlac

Rehabilitation of existing Dike along Lucung River, (Culatingan Section, Left Bank), Concepcion, Tarlac is a DPWH-tracked public work in CONCEPCION (TARLAC), TARLAC, Region III. Reported contract value: ₱48,342,638.69. Status: Reported complete (DPWH). Contractor on record: HIGH STRENGTH DEV CORP / T2B3 BUILDERS AND SUPPLIES CORP. Figures trace to sumbong.

CONCEPCION (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along Camiling River Left Bank Phase II-2, Poblacion D to G Section, Poblacion D to G, Camiling, Tarlac
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002779

₱320,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0005156

₱20,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002922

₱811,709,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0005139

₱71,901.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004769

₱50,540.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004759

₱542,182.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,342,638.69

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

October 16, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.