Rehabilitation / Major Repair of Flood Control Structure22CK0081

Rehabilitation of Dike along Lucung River, (Malupa Section, Right Bank), Concepcion, Tarlac (Sta. 2+206 to Sta. 2+688)

Rehabilitation of Dike along Lucung River, (Malupa Section, Right Bank), Concepcion, Tarlac (Sta. 2+206 to Sta. 2+688) is a DPWH-tracked public work in CONCEPCION (TARLAC), TARLAC, Region III. Reported contract value: ₱60,202,410.54. Status: Reported complete (DPWH). Contractor on record: HIGH STRENGTH DEV CORP / T2B3 BUILDERS AND SUPPLIES CORP. Figures trace to sumbong.

CONCEPCION (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control Structure Along Tarlac River Control Right Dike, Colibangbang-Nancamarinan Section, Paniqui, Tarlac
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002779

₱320,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0005156

₱20,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002922

₱811,709,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0005139

₱71,901.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004769

₱50,540.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004759

₱542,182.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱60,202,410.54

Progress

Reported complete (DPWH)

Start Date

March 26, 2022

Target End

January 5, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.