Construction of Flood Mitigation Structure23HH0124

Construction of Flood Mitigation Structure, Brgy. Sambag 1 , Cebu City

Construction of Flood Mitigation Structure, Brgy. Sambag 1 , Cebu City is a DPWH-tracked public work in CEBU CITY (CAPITAL) (CEBU), CEBU, Region VII. Reported contract value: ₱4,944,995.26. Status: Reported complete (DPWH). Contractor on record: MATROSON BUILDERS & ENGINEERING SERVICES. Figures trace to sumbong.

CEBU CITY (CAPITAL) (CEBU), CEBU, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. Sambag 1 , Cebu City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu City District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

Possible match · 74%

CUSTOMIZED THREE LAYER TUBULAR METAL RACKS

₱1,199,000.00 · MATROSON BUILDERS & ENGINEERING SERVICES

Contractor

1 projects · ₱4.9M total · 0 flags

4. Implementation

Contract Amount

₱4,944,995.26

Progress

Reported complete (DPWH)

Start Date

October 10, 2023

Target End

February 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.