Rehabilitation / Major Repair of Flood Control Structure22CK0110

Rehabilitation of Existing Dike along Bulalo River, Bantog Section, Downside (D/S) of Check Gate

Rehabilitation of Existing Dike along Bulalo River, Bantog Section, Downside (D/S) of Check Gate is a DPWH-tracked public work in LA PAZ (TARLAC), TARLAC, Region III. Reported contract value: ₱19,191,837.84. Status: Reported complete (DPWH). Contractor on record: RAIK CONST AND DEVELOPMENT CORP FORMERLY: RAIK CONST AND SUPPLY. Figures trace to sumbong.

LA PAZ (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control Structure Along Tarlac River Control Right Dike, Colibangbang-Nancamarinan Section, Paniqui, Tarlac
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002779

₱320,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0005156

₱20,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002922

₱811,709,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0005139

₱71,901.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004769

₱50,540.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004759

₱542,182.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱19,191,837.84

Progress

Reported complete (DPWH)

Start Date

June 29, 2022

Target End

April 12, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.