Flood Control and Drainage17DN0128

CONSTRUCTION OF RETAINING WALL ALONG M.L. QUEZON EXTENSION, BRGY. SAN ROQUE, ANTIPOLO CITY

CONSTRUCTION OF RETAINING WALL ALONG M.L. QUEZON EXTENSION, BRGY. SAN ROQUE, ANTIPOLO CITY is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱17,297,556.11. Status: Reported complete (DPWH). Contractor on record: ALPHA. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱3,700,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Drainage Canal along Floodway Road Westbank, Rizal
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-17-0000692

₱100,000,000.00 · FY2017

Released to National Electrification Administration (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

831 projects · ₱32.1B total · 0 flags

4. Implementation

Contract Amount

₱17,297,556.11

Progress

Reported complete (DPWH)

Start Date

October 2, 2017

Target End

April 29, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.